Saturday, April 5, 2014

Programs which determine cost in Project Costing module

Programs which determine cost in Project Costing module



We should run the below programs to determine the costs in Project Costing Module

To determine labor costs run the below programs

1/  PRC: Distribute Labor Costs (or)  PRC: Distribute Labor Costs for a Range of Projects

To determine cost for usage and miscellaneous transactions run the below program

1/ PRC: Distribute Usage and Miscellaneous Costs

To determine the supplier cost run the below programs

1/ PRC: Interface Supplier Costs

2/ PRC: Distribute Supplier Cost Adjustments (or) PRC: Distribute Supplier Costs Adjustments for a Range of Projects

To determine expense report cost run the below programs

1/ PRC: Interface Expense Reports from Payables

2/ PRC: Distribute Expense Report Adjustments

To determine costs for borrowed and lent accounting run the below program


1/ PRC: Distribute Borrowed and Lent Amounts


To determine the burden cost run the below program

1/ PRC: Create and Distribute Burden Transactions


The above program creates burden transactions for projects based on the method to store burden costs.


To determine total burdened cost run the below program


1/ PRC: Distribute Total Burdened Costs


The above program creates total burdened cost distribution lines for all transactions on a burdened project.